JUNE 2014: Peoples Republic of China
From News, By admin, Update November 17, 2015 at 12:36 am
ALBA OS entered into an agreement with a well-known offshore drilling contractor to supply two; experienced Commissioning Manager’s to carry out the following duties on two new CJ46 model Jack – Up drilling rigs which were ABS classified ?for a period of six months.
The following work scope was implemented and successfully carried out by the end of March 2015 for the first rig –
1) Review and clarify the status and quality of the ship yard Mechanical Completions & Commissioning documents which are currently in force, and IF; required provide and produce suitable commissioning documents where they are lacking and or substandard, by International & Class Standards
2) Take control of the Mechanical Completions & Commissioning procedures and ensure they are managed in a proper Industry Standard method on a day to day basis and recorded correctly.
3) Build and compile a complete library of Commissioning documents, which will pass scrutiny by any potential third party inspections company, to ensure the rig has been produced to Industry & Class Standards as a minimum.
4) Provide onsite training to the Clients Superintendents who are at present responsible for the Commissioning Phase of the Projects
5) Provide a detailed daily report to the Clients site manager.
Key areas to concentrate on the Commissioning phase of the project specifically but; not limited to the following-
- Liaise between the Clients Superintendents onsite and their shipyard counterparts.
- Review Commissioning procedures provided by the shipyard and amend or comment as required.
- Provide expertise in relation to good industry standard practices prior to commissioning operations commencing and during all commissioning procedures.
- Conduct “kick off” meeting with the Client & Shipyard representatives to discuss the particular areas of concern.
- Discuss the plan for the Commissioning Schedule.
- Firm up the single Commissioning point of contact with the Shipyard management in relation to but not limited to the following –
- Mile Stones for Commissioning
- Any potential road blocks to the Commissioning Plan
- Confirm any FAT visits for key equipment to arrange and schedule.